After exporting the schedule to Primavera Risk Analysis, the project final date is not the same. Some activities don't have the same start and finish dates.
R
Answer by
Robert Polubinski
You will have to ask the support technicians from Oracle, because there is nowhere mentioned about this procedure. I have tried looking for the Export function, but I couldn't find anything.
Use the official website to learn more about it and get in touch with the support team. They will provide the necessary details to get the job done.
I know how to quantify the impact of a Risk on activities. For example, by saying more likely impact would be 10d then it will add 10d to the respective activity.
What about opportunities? When I assign an opportunity to a task and then tried to fill the quantified section of the risk register it only accepts positive number of days (example 10d) which work similar to risk (no opportunities) meaning it adds 10d to the original duration. This is not what opportunity is. Opportunity is to reduce the duration by some amount (example 10d). It doesn't accept negative numbers, so how do you suggest to use the risk register to implement it?
J
Answer by
Julia Bocchetta
Since there is no exact information about this procedure, you will have to analyze the results posted on various websites listed through the search engine. I have seen some documents (PDF) files that give examples of how opportunities work. I recommend checking the Google Search results in order to analyze these websites.
After exporting the schedule to Primavera Risk Analysis, the project final date is not the same. Some activities don't have the same start and finish dates.
You will have to ask the support technicians from Oracle, because there is nowhere mentioned about this procedure. I have tried looking for the Export function, but I couldn't find anything.
Use the official website to learn more about it and get in touch with the support team. They will provide the necessary details to get the job done.
Website: http://www.oracle.com/us/products/applications/primavera/risk-analysis/resources/index.html
I know how to quantify the impact of a Risk on activities. For example, by saying more likely impact would be 10d then it will add 10d to the respective activity.
What about opportunities? When I assign an opportunity to a task and then tried to fill the quantified section of the risk register it only accepts positive number of days (example 10d) which work similar to risk (no opportunities) meaning it adds 10d to the original duration. This is not what opportunity is. Opportunity is to reduce the duration by some amount (example 10d). It doesn't accept negative numbers, so how do you suggest to use the risk register to implement it?
Since there is no exact information about this procedure, you will have to analyze the results posted on various websites listed through the search engine. I have seen some documents (PDF) files that give examples of how opportunities work. I recommend checking the Google Search results in order to analyze these websites.